Years Behind Schedule and Millions Over Budget, Silver Spring Transit Center May Open Soon

Approaching five years behind schedule and tens of millions of dollars over budget on the Silver Spring Transit Center, Montgomery County is nearly ready to hand the project over to Metro.

04/21/2015

(Photo by Kevin P. Casey/Getty Images)

Silver Spring Transit Center Report: Risk Of Falling Concrete

A new report on Silver Spring Transit Center warns that the public will be at increased risk from falling concrete chunks unless interior beams and girders are reinforced.

04/30/2014

credit: KAREN BLEIER/AFP/Getty Images

Delayed Silver Spring Transit Center Update Coming

The Montgomery County Council is going to get an update on remediation plans for the Silver Spring Transit Center.

07/23/2013

(Photo credit: KAREN BLEIER/AFP/Getty Images)

Montgomery County Approves $7.5 Million More For Transit Center

The Montgomery County Council has approved an additional $7.5 million for construction of the troubled Silver Spring Transit Center.

04/03/2013

US-CONSTRUCTION WORK

Builder Blames Montgomery Co. for Transit Hub

The contractor that has overseen construction of the troubled Silver Spring Transit Center is blaming Montgomery County officials for problems that have plagued the project.